PowerChute is installed on a physical machine outside the Cluster, configured for a Single/Redundant UPS configuration with 2 nodes in a Cluster. The option to Turn off the Outlet Group is enabled on the Shutdown Settings page, Delay Host Maintenance Mode is enabled on the Virtualization Settings page. No shutdown command file or SSH action configured. The durations in this example are as follows:
When a critical UPS event, such as On Battery occurs, the following sequence is triggered.

The Outlet Group will turn off after the Power Off Delay (configurable on the Configuration – Outlet Group page in the NMC user interface) has elapsed.
If registered with the Main Outlet Group, the UPS will wait for any Switched Outlet Groups to turn off before the Main Outlet Group turnoff starts.
If registered with a Switched Outlet Group, only that delay is counted down.
It is recommended that the Outlet Group Power Off Delay is configured to allow enough time for the operating system shutdown to complete. You should allow extra time to ensure that the Outlet Group does not turn off before the operating system.
PowerChute is installed as a VM inside the Cluster, configured for a Single/Redundant UPS configuration with 2 nodes in a Cluster. HA is enabled on the Cluster and there is an internal vCenter Server Appliance. The option to Turn off the Outlet Group is enabled on the Shutdown Settings page, Delay Host Maintenance Mode is enabled on the Virtualization Settings page. No shutdown command file or SSH action configured. The durations in this example are as follows:
When a critical UPS event, such as On Battery occurs, the following sequence is triggered.

The Outlet Group will turn off after the Power Off Delay (configurable on the Configuration – Outlet Group page in the NMC user interface) has elapsed.
If registered with the Main Outlet Group, the UPS will wait for any Switched Outlet Groups to turn off before the Main Outlet Group turnoff starts.
If registered with a Switched Outlet Group, only that delay is counted down.
It is recommended that the Outlet Group Power Off Delay is configured to allow enough time for the operating system shutdown to complete. You should allow extra time to ensure that the Outlet Group does not turn off before the operating system.
PowerChute is installed on a physical machine outside the Cluster, configured for a Single/Redundant UPS configuration with 2 nodes in a Cluster. The option to Turn off the Outlet Group is enabled on the Shutdown Settings page, Delay Host Maintenance Mode is enabled on the Virtualization Settings page. A shutdown command file is configured. The durations in this example are as follows:
When a critical UPS event, such as On Battery occurs, the following sequence is triggered.

The Outlet Group will turn off after the Power Off Delay (configurable on the Configuration – Outlet Group page in the NMC user interface) has elapsed.
If registered with the Main Outlet Group, the UPS will wait for any Switched Outlet Groups to turn off before the Main Outlet Group turnoff starts.
If registered with a Switched Outlet Group, only that delay is counted down.
It is recommended that the Outlet Group Power Off Delay is configured to allow enough time for the operating system shutdown to complete. You should allow extra time to ensure that the Outlet Group does not turn off before the operating system.
PowerChute is installed as a VM inside the Cluster, configured for a Single/Redundant UPS configuration with 2 nodes in a Cluster. HA is enabled on the Cluster and there is an internal vCenter Server Appliance. The option to Turn off the Outlet Group is enabled on the Shutdown Settings page, Delay Host Maintenance Mode is enabled on the Virtualization Settings page. A shutdown command file is configured. The durations in this example are as follows:
When a critical UPS event, such as On Battery occurs, the following sequence is triggered.

The Outlet Group will turn off after the Power Off Delay (configurable on the Configuration – Outlet Group page in the NMC user interface) has elapsed.
If registered with the Main Outlet Group, the UPS will wait for any Switched Outlet Groups to turn off before the Main Outlet Group turnoff starts.
If registered with a Switched Outlet Group, only that delay is counted down.
It is recommended that the Outlet Group Power Off Delay is configured to allow enough time for the operating system shutdown to complete. You should allow extra time to ensure that the Outlet Group does not turn off before the operating system.
PowerChute is installed on a physical machine outside the Cluster, configured for a Single/Redundant UPS configuration with 2 nodes in a Cluster. The option to Turn off the Outlet Group is enabled on the Shutdown Settings page, Delay Host Maintenance Mode is enabled on the Virtualization Settings page. A shutdown command file is configured. Execute Command File after Host Shutdown is enabled, with a delay of 30 seconds applied. The durations in this example are as follows:
When a critical UPS event, such as On Battery occurs, the following sequence is triggered.

The Outlet Group will turn off after the Power Off Delay (configurable on the Configuration – Outlet Group page in the NMC user interface) has elapsed.
If registered with the Main Outlet Group, the UPS will wait for any Switched Outlet Groups to turn off before the Main Outlet Group turnoff starts.
If registered with a Switched Outlet Group, only that delay is counted down.
It is recommended that the Outlet Group Power Off Delay is configured to allow enough time for the operating system shutdown to complete. You should allow extra time to ensure that the Outlet Group does not turn off before the operating system.
PowerChute is installed as a VM inside the Cluster, configured for a Single/Redundant UPS configuration with 2 nodes in a Cluster. HA is enabled on the Cluster and there is an internal vCenter Server Appliance. The option to Turn off the Outlet Group is enabled on the Shutdown Settings page, Delay Host Maintenance Mode is enabled on the Virtualization Settings page. A SSH action is configured to execute before host shutdown, with a delay of 30 seconds applied. The durations in this example are as follows:
When a critical UPS event, such as On Battery occurs, the following sequence is triggered.

The Outlet Group will turn off after the Power Off Delay (configurable on the Configuration – Outlet Group page in the NMC user interface) has elapsed.
If registered with the Main Outlet Group, the UPS will wait for any Switched Outlet Groups to turn off before the Main Outlet Group turnoff starts.
If registered with a Switched Outlet Group, only that delay is counted down.
It is recommended that the Outlet Group Power Off Delay is configured to allow enough time for the operating system shutdown to complete. You should allow extra time to ensure that the Outlet Group does not turn off before the operating system.
By default, the outlet group Power Off Delay will be the same value as the Low Battery duration configured on the NMC. PowerChute will automatically increase the Power Off Delay for the outlet group it is registered with, if the total shutdown time it needs is greater than the Power Off Delay.
The total shutdown time includes the following values:
VM/vApp Shutdown and Startup Duration
vCenter Server Appliance Shutdown Duration
OmniStack Virtual Controller Shutdown and Startup Duration
Delay Host Maintenance Mode Duration
Execute Command File after Host Shutdown delay
Shutdown Command File Duration
SSH Action Duration
Built-in delay of 2 minutes (this consists of a 10 second OS shutdown delay and a 60 second OS shutdown duration; rounded up)
The time required to gracefully shut down your operating system is not covered by the total shutdown time, as PowerChute cannot determine how long it will take to complete. The Power Off Delay for the outlet group should be long enough for the OS to gracefully shut down. You should add extra time to allow for unforeseen circumstances. The Low Battery Duration set on the NMC should be equal to or greater than the Power Off Delay for the outlet group. |

Copyright
© 2020 Schneider Electric
All rights reserved
http://www.apc.com
Last Updated: 17 December, 2020
990-4595H
Send
any comments on this help to:
IE-PowerChute-feedback@schneider-electric.com